[meteorite-list] Dawn's Early Light - April 2006
From: Ron Baalke <baalke_at_meteoritecentral.com>
Date: Fri Apr 7 00:21:08 2006 Message-ID: <200604070059.k370xko28705_at_zagami.jpl.nasa.gov> D A W N ' S E A R L Y L I G H T April 2006 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - The ninth issue of the Dawn team newsletter, Dawn's Early Light, has been posted on the Dawn website. Follow the links below to view individual articles, or obtain the formatted pdf version. We look forward to obtaining your feedback. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . http://www-ssc.igpp.ucla.edu/dawn/newsletter/html/20060405/dawnintegration.html Dawn Proceeds to Launch Christopher T. Russell Dawn Principal Investigator, UCLA On March 27, NASA Associate Administrator Rex Geveden reinstated the Dawn mission, after it had been cancelled on March 2nd. The Dawn team is very grateful that NASA recognized the work that the project has accomplished to reduce technical, schedule and cost risk, and committed the funds needed to complete the mission. The project team has been directed to resume integration and testing activities, and develop a detailed project schedule and cost profile to support a launch between June and August of 2007. The project estimates it will need <$54M in additional funds. All of us on the Dawn project are grateful for the tremendous outpouring of support from the community during the stand down and following cancellation. Special thanks go to the European Space Agency and to the Italian Space Agency for offers of support during the operational phase of the mission and the strong backing and commitment from Orbital Sciences Corporation and the Jet Propulsion Laboratory to give Dawn high priority in obtaining the resources and personnel needed to proceed smoothly to launch. The support of the German Space Agency, DLR, is also much appreciated. Over the next two months, Dawn will be staffing up and returning to the level of effort necessary to proceed to the mid-2007 launch. Due to the use of a Mars Gravity Assist in 2009, which fixes the timing of subsequent events, the launch delay does not affect the timing of the arrivals and departures at Vesta and Ceres, nor the science operations. However, if we were not able to launch by the end of October 2007, then the dual asteroid mission would not be possible for another 15 years. Thus, it is very fortunate that this mission was approved to go forward at this time. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . http://www-ssc.igpp.ucla.edu/dawn/newsletter/html/20060405/dawnstatus.html Dawn Status Report Carol A. Raymond Dawn Deputy Principal Investigator, JPL Dawn emerges from the five-month stand down period with positive closure on several technical issues, and some new team members. Keyur Patel has been named the new Project Manager at JPL. Keyur's recent experience was as Deputy Project Manager on Deep Impact through its successful encounter with Tempel 1. Ann Grandfield has been promoted to Project Manager (from Deputy) at Orbital Sciences Corporation. There is good news regarding the ion propulsion system components, namely the xenon tank and the power processing units, which raised concerns of NASA managers and contributed to their decision to direct the project to stand down. The Dawn flight xenon tank has been an item of concern since a qualification tank and a flight spare tank ruptured at lower-than-expected pressures during testing. The tank is a composite overwrapped pressure vessel (COPV) with a titanium liner. While the actual flight tank had been tested and performed at pressures well above the expected flight and ground pressures, there was lingering concern that the cause of the qual and spare tank failures needed to be understood to fully qualify the flight tank. An Independent Review Team (IRT) team was formed to review the issues. The project decided to reduce the xenon load from 450 to 425 kg to add an extra margin of safety (with no impact on planned science operations). The IRT team concluded that the tank was flightworthy in Sept 2005, and was succeeded by an Independent Technical Authority (ITA) review. After extensive materials testing, the cause of the qual/spare tank failures was determined to be due to manufacturing anomalies that had no bearing on the integrity of the flight tank. The ITA issued their draft report on March 17th, concluding that the Dawn flight xenon tank was flightworthy. Figure 1. Dawn flight COPV tank. The tank, which was integrated last fall, has a safety factor >2 for a xenon load of 425 kg. Several test failures of the Power Processing Units (PPUs) of the ion propulsion system also were a cause of concern that contributed to the mission stand down. The PPUs had experienced parts failures and unplanned shutdowns during testing. A PPU tiger team was formed to assess the PPU design and provide independent assessment of the cause of the testing anomalies. The team concluded that the design was sound, devised methods to test for defects in parts similar to the ones that failed, and explained the shutdowns as indicating the possible need to adjust an internal parameter value. The tiger team recommended an extended "run-in" test of the two identical units, in vacuum for 500-1000 hours, to validate parts quality and operational stability. The run-in testing procedures have been written and tested and the actual testing is due to start immediately. The Dawn PPU design was inherited from the Deep Space 1 (DS1) mission. The PPU flown on DS1 operated flawlessly for 16265 hours, while the two Dawn PPUs together are expected to operate for about 48000 hours. A minor change was made to the DS1 PPU design to improve the response to a serious grid short. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . http://www-ssc.igpp.ucla.edu/dawn/newsletter/html/20060405/dawnintegration.html Dawn Spacecraft Nearing Final Integration Carol A. Raymond Dawn Deputy Principal Investigator, JPL During the stand down the team has been working on developing and vetting test procedures and dry-running them on the testbed. The team is anxious to integrate the instruments, which have been stored at Orbital since November, and begin comprehensive spacecraft testing. Final delivery of the second (re-worked) Attitude Control Electronics Unit, the PPUs, and re-worked Digital Control Interface Units are pending. The ion thrusters are the last items to be integrated. Figure 2. State of the Dawn spacecraft as of last October (same as current state). Reaction wheels and coarse sun sensors are visible on the upper (+Z) deck, and an ion thruster mounting sleeve at bottom. Spacecraft assembly is about 90% complete. Figure 3. View of spacecraft showing harness and subsystem boxes in the high bay at Orbital. Boxes are integrated to flight panels that are laid flat for testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Received on Thu 06 Apr 2006 08:59:46 PM PDT |
StumbleUpon del.icio.us Yahoo MyWeb |